POST-CONSTRUCTION APPLICATION
Concrete slab foundations. Apply at rate of 5 liters
per linear meter along router edge of the foundation, under
the slab, and at all cracks and expansion joints.
Application methods may be through the sub-slab injection by
drilling holes in the slab or through foundation walls from
the outside. Inject the emulsion through the holes and along
the cracks and expansion joints. For shallow (less than 30
cm) foundation walls, apply the emulsion by trenching.
Basements. Use at a rate of 5 liters per linear
meter by trenching outside foundation walls and by rodding
underneath basement floor, along the inside of foundation
walls. along cracks, around sewer pipes, conduits and piers.
Hollow block foundations. Apply at a rate of 2.5
liters per linear meter of wall by drilling or probing.
Re-entry period. Do not enter the building within 24
hours after spraying.
|